           SECTION-A
Q1. a) Fill in the Blanks           1×1=10
   i. Construction management helps to properly utilize ____________________.
  ii. It is usual practice to award contract to the lowest qualified __________.
   iii. Bar chart is also known as ___________________ .
   iv. There is overlapping and duplication of responsibility in ____________________
   v. Bricks are stacked near the construction site with height of stack not more than ________
   vi. Job diary is an important document for ______________
   vii. In PWD, measurement book is recorded & maintained by _____________.
   viii. Financial year is always closed on _____________ every year.
   ix. The officer having D.D.O. powers in PWD system is _________________ .
   x. Daily labour is paid on the basis of attendance marked on _____________ .
(b) True/ False statements 5×1=5
    i. Site investigations are recommended by engineer to owner. T/F
   ii. Functional organisation is also known as military organisation. T/F
    iii. D.F.R. is an important book dealing with accounts. T/F
   iv. Final bills of payment are printed on white paper. T/F
   v. The maximum time in which an activity can be completed is termed as ‘crash time’. T/F
                   SECTION-B
Q2. Attempt any five questions.                                  5×6=30
    I. Define the important resources of construction industry.
    II. Differentiate between PERT and CPM.
   III. What do you mean by trade union? Write down functions performed by trade unions.
   IV. Write down the advantages and disadvantages of time rate system.
    V. Explain the duties of junior engineer.
    VI. Differentiate between imprest and temporary advance.
    VII. Write down the main features of PWD system of Accounts.
   VIII. Define pre-tender stage of construction planning and give the detail of work done by contractor         during this stage.
                   SECTION-C
Q3. Attempt any three questions.                            3×10=30
  I. What do you mean by construction management? Explain the various functions of construction         management.
   II. Define organization. Write down its types & list the various advantages and disadvantages of any        one type of organisation.
   III. Explain the main stages followed in the completion projects for public works.
   IV. What is the importance of controlling and recording progress of work? Write down different            methods of recording progress and explain measurement book in detail.
CMA Civil 6th Semester Diploma Dec 2015 Solved Question Paper
           SECTION-A
Q1. a) Fill in the Blanks           1×1=10
   i. Construction management helps to properly utilize available resources.
  ii. It is usual practice to award contract to the lowest qualified Bidder .
   iii. Bar chart is also known as Gantt chart .
   iv. There is overlapping and duplication of responsibility in Functional Organisation.
   v. Bricks are stacked near the construction site with height of stack not more than _______
   vi. Job diary is an important document for Recording Process .
   vii. In PWD, measurement book is recorded & maintained by Junior engineer (J.E) .
   viii. Financial year is always closed on 31st March every year.
   ix. The officer having D.D.O. powers in PWD system is Divisional officer (XEN) .
   x. Daily labour is paid on the basis of attendance marked on Muster Roll .
(b) True/ False statements 5×1=5
    i. Site investigations are recommended by engineer to owner. (False)
   ii. Functional organisation is also known as military organisation. (False)
    iii. D.F.R. is an important book dealing with accounts. (True)
   iv. Final bills of payment are printed on white paper. (False)
   v. The maximum time in which an activity can be completed is termed as ‘crash time’. (True)
Construction management helps to properly utilize available resources.
 Â
It is usual practice to award contract to the lowest qualified Bidder .
  Â
Bar chart is also known as Gantt chart .
  Â
There is overlapping and duplication of responsibility in Functional Organisation.
 Â
Bricks are stacked near the construction site with height of stack not more than _______
  Â
Job diary is an important document for Recording Process .
  Â
In PWD, measurement book is recorded & maintained by Junior engineer (J.E) .
  Â
Financial year is always closed on 31st March every year.
  Â
The officer having D.D.O. powers in PWD system is Divisional officer (XEN) .
  Â
Daily labour is paid on the basis of attendance marked on Muster Roll .
Â
CMAÂ 6th Semester CIVIL Dec 2015 Diploma Solved Paper Click Here
Important resources of construction industry.
Differentiate Between PERT and CPM.
Trade union and its functionsÂ
Advantages and disadvantages of time rate system.
Duties of junior engineer.
Differentiate between imprest and temporary advance.
Main features of PWD system of Accounts.
Pre-tender stage of construction planningÂ
CMAÂ 6th Semester CIVIL Dec 2015 Diploma Solved Paper Click Here
Construction management and various functions of construction management.
  Â
Organization. its typesÂ
  Â
Main stages followed in the completion projects for public works.
  Â
Importance of controlling and recording progress of work