                                        SECTION-A

Q1. Do as directed.                                                                                     15×1=15

  1. Construction is the ultimate objective of a design.
  2. Bar Chart is also known as Gantt chart.
  3. Job diary is an important document for recording progress.
  4. DPC is laid to protect the building from moisture.
  5. Accidents are mishappening  on construction projects.
  6. Payment of wages Act was passed in the year 1936.   
  7. Military organization is the simplest  and the earliest form of organization.
  8. Daily labor is paid on the basis of attendance marked on muster roll        .
  9. First stage in Construction is conception                .
  10. Financial year is always closed on 31st march every year.

b) State true or false.

  1. Design is a function of construction management.           (False)
  2. Span control is not the principle of organization.               (False)
  3. Control of quality delays the completion of project.          (False)
  4. Line organization is flexible in nature.                                  (False)
  5. Temporary advance can be recouped from time to time. (False)

              SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30

  1. What is relationship between owner and engineer in a construction team?
  2. Differentiate between PERT & CPM.
  3. What are the resources of Construction Industry?
  4. What is the difference between Imprest & Temporary advance.
  5. What are the causes of accidents on construction site?
  6. Define scheduling. Enlist its important advantages.
  7. Explain the following:(any two)

           i) Activity         ii)Event        iii) Critical Path

        8.Enlist the important stages of inspection in construction work?

     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

  1. Discuss the various stages in planning a construction project.
  2. Explain Line & staff organization. What are its advantages?
  3. What are the functions of construction management?
  4. Explain the term wages. What are different forms of wages?
  5. What is the difference between stock & tool and plant accounts?

Construction and Accounts CMA 6th Sem Civil Exam /5170/May 2019

Section a FILL IN THE BLANKS Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper

Construction is the ultimate objective of a design.

 

Bar Chart is also known as Gantt chart.

 

Job diary is an important document for recording progress.

DPC is laid to protect the building from moisture.

Accidents are mishappening  on construction projects.

Payment of wages Act was passed in the year 1936.   

Military organization is the simplest  and the earliest form of organization.

Daily labor is paid on the basis of attendance marked on muster roll

First stage in Construction is conception                

Financial year is always closed on 31st march every year.

b) State true or false.

Download Previous Year Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Click Here

Section B :Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper

Relationship between owner and engineer in a construction team

Differentiate between PERT & CPM.

Resources of Construction Industry

Difference between Imprest & Temporary advance.

Causes of accidents on construction site

Scheduling its important advantages.

Explain the following:(any two)

           i) Activity         ii)Event        iii) Critical Path

Important stages of inspection in construction work

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper Click Here

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018

Section c :-Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019

Various stages in planning a construction project.

Line & staff organization and its advantages

Functions of construction management 

term wages. What are different forms of wages

Difference between stock & tool and plant accounts

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Contact Us
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ENGINEERING CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
er.jaswinder kumar
Senior Lecturer

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top