Construction Management and Accounts CMA 6th Sem/Civil/5170/May 2019

Download Previous year Diploma Paper of Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Paper.

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019

                                        SECTION-A

Q1. Do as directed.                                                                                                              15×1=15

  1. The art of planning, co-coordinating and controlling various activities of a construction project is known as Reduce.
  2. Bar chart is also known as  Gantt chart.
  3. Line organization is not suitable for large projects.
  4. Fire extinguishers should be installed at the construction site to prevent fire hazards.
  5. The minimum wages Act was passed in the year 1948.
  6. A notebook which records the quantities of work done at the site periodically is termed as measurement book.
  7. Quality control is achieved through routine inspection.
  8. An event occurring unexpectedly during construction work is known as accident.
  9. A book which records cash transactions related to receipts and payments is cash book.
  10. Military organization is the  simplest and the earliest form of organization.

b) State true or false.

  1. The function of engineer is to arrange finances for the project.  (False)
  2. CPM is activity based network.                           (True)                  
  3. Motivation of employees is not the need of organization.           (False)
  4. The muster roll is used to mark the attendance of labour.           (True)
  5. About 80 percent accidents are caused due to unsafe practices and shear negligence.   (True)

              SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30

  1. What are the functions of owners in construction team?
  2. Differentiate between PERT and CPM.
  3. What are the advantages of Line organization?
  4. Differentiate between direct and indirect costs?
  5. What are the main points to be kept in mind for quality control of masonry?
  6. Describe briefly the safety measures forformwork.
  7. Differentiate between Imprest and Temporary Advance.
  8. Define scheduling. Enlist its some importantadvantages.
  9. Define the following. (anytwo)
    1. Activity         b)Event              c)Dummy activity                  d) critical path.
  10. What are the limitations of barcharts?

     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

  1. What are the various functions of construction management? Discuss them briefly.
  2. Explain the resources for construction industry.
  3. Explain the principle of storing and stacking materials at site?
  4. Discuss the various stages in planning a construction project.
  5. Explain the stages in projects for public works.
  6. Explain functional organization. What are its advantages?

Construction and Accounts CMA 6th Sem Civil Exam /5170/May 2019

MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ENGINEERING CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
er.jaswinder kumar
Senior Lecturer

Construction and Accounts CMA 6th Sem Civil Exam /5170/May 2019

Section a FILL IN THE BLANKS Water Supply & Waste Water Engg. 4th Sem Civil/0514/Dec 2015 Paper

The art of planning, co-coordinating and controlling various activities of a construction project is known as Reduce.

Bar chart is also known as Gantt chart.

 

Line organization is not suitable for large projects.

Fire extinguishers should be installed at the construction site to prevent fire hazards.

The minimum wages Act was passed in the year 1948.

 

A notebook which records the quantities of work done at the site periodically is termed as measurement book.

Quality control is achieved through routine inspection.

An event occurring unexpectedly during construction work is known as accident.

A book which records cash transactions related to receipts and payments is cash book.

Military organization is the  simplest and the earliest form of organization.

 

b) State true or false.

(True)                  

 

Download Previous Year Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Click Here

Section B :Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019

functions of owners in construction team.

Differentiate between PERT and CPM.

Advantages of Line organization

Differentiate between direct and indirect costs

Main points to be kept in mind for quality control of masonry

Define scheduling. and  its important advantages.

a) Activity         b)Event              c)Dummy activity                  d) critical path

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Paper Click Here

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019

Section c :-Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019

Various functions of construction management

Resources for construction industry.

Principle of storing and stacking materials at site

Different stages in planning a construction project.

Stages in projects for public works.

functional organization its advantages

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Contact Us

Download Previous year Diploma Paper of Concrete Technology CT 4th Sem Civil/0512/May 2017 Paper

Concrete Technology CT 4th Sem Civil/0512/May 2017 Paper

                                                SECTION-A

Q1. Do as directed.                                                                                                                      15×1=15

  1.  The mixture of cement, fine aggregate, and water is called concrete.

  2. Le-Chatelier  apparatus is used for soundness test of cement

  3. The initial setting time of OPC is 30 minut.

  4. Strength of cement is also called compressive strength

  5. The weight of one bag of cement is 50 kg.

  6. Ready mixed concrete is also called M.C concrete.

  7. Gypsum is added in cement for control setting time.

  8. Cement is always batched by weight

  9. Round and smooth aggregates increase the the workability.

  10. Slump of concrete is measured to test workability of concrete

     b) State True or False.

  1. When fully saturated, the bulking of sand is 100%.                                  (False)

  2. The strength of concrete is independent of water contents in it.           (True)

  3. If the mix is dry, the slump is zero.                                                               (False)

  4. Strength of cement is independent of storage period.                              (True)

  5. The volume of one bag of cement is 0.05m³.                                             (False)

              SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30

  1. Write the advantages and disadvantages of concrete?

  2. What do you mean by batching? What are the different methods of batching?

  3. Explain the slump test of concrete?

  4. What are the various types of concrete mixer commonly used? Explain in

  5. What is difference b/w segregation and bleeding?

  6. What is the purpose of using admixture in concrete?

  7. Give the importance of non-destructive test?

  8. What is curing of concrete? What are the different methods of curing?

  9. What are the various methods of transportation of concrete?

     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

  1. What do you mean by workability? Describe compacting factor Test
  2. Explain the properties of concrete in the hardened State ?
  3. Write short note on
    1. Bulking of
    2. Non-destructive test
    3. Segregation
    4. Concreting in hot weather
  4. Give the requirement of a ware house for the storage of concrete? What precaution will be taken while storing cement in ware house?

Concrete Technology CT 4th Sem Civil/0512/MAY 2017 Solved Paper

Section a FILL IN THE BLANKS cONCRETE TECHNOLOGY MAY 2017 paper

The mixture of cement, fine aggregate, and water is called concrete.

 

Le-Chatelier  apparatus is used for soundness test of cement

 

The initial setting time of OPC is 30 minute.

 

Strength of cement is also called compressive strength

 

The weight of one bag of cement is 50 kg.

 

Ready mixed concrete is also called R.M.C concrete.

Gypsum is added in cement for control setting time.

Cement is always batched by weight.

 

Round and smooth aggregates increase the the workability.

 

Slump of concrete is measured to test workability of concrete.

 

b) State true or false.

                         (True)

Download Previous Year Concrete Technology PSBTE Diploma Solved Paper May 2017 Click Here

Section B : cONCRETE TECHNOLOGY PAPER MAY 2017 PAPER

Advantages and disadvantages of concrete

Slump test of concrete

 

Various types of concrete mixer commonly used

 

Difference b/w segregation and bleeding

 

Purpose of using admixture in concrete

Importance of non-destructive test

Uses of fibre reinforced concrete.

 

Curing of concrete and  different methods of curing

Various methods of transportation of concrete

Various methods of transportation of concrete

Concrete Technology Civil 4th Semester  PSBTE Diploma Solved May 2017 Paper Click Here

Concrete Technology CT 4th Sem Civil/0512/may 2017 Solved Paper

Section c solved concrete technology dec 2017 paper

 1.workability

2. Describe compacting factor Test

 

Properties of concrete in the hardened State 

 

    1. Bulking of Sand 
    2. Non-destructive test
    3. Segregation
    4. Concreting in hot weather
  1.  

1.Requirement of a ware house for the storage of concrete 

2.precaution will be taken while storing cement in ware house?

Concrete Technology CT Diploma 4th Semester Civil/0512/May 2017 Paper Contact Us
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ENGINEERING CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
er.jaswinder kumar
Senior Lecturer
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ENGINEERING CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
er.jaswinder kumar
Senior Lecturer

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top