Download Previous year Diploma Paper of Production Planning and Costing 6th Sem Dec 2016 Automobile Diploma Paper
Production Planning and Costing 6th Sem Dec 2016 Automobile Diploma Paper
                SECTION-A
Q1. A) Fill in the blanks: 5×1=5
1. BIS stands for _____________
2. Process production is a ________ type of production
3. Catalogue price = _______________
4. Rent of building, depreciation cost comes under __________ overhead.
5. ______ is the process of predicting events, in advance.
B) Define the following: 5×2=10
1. Depreciation
2. Quality circle
3. Inspection
4. Follow up
5. Batch production
            SECTION-B
Q2. Attempt any five questions.                                  5×6=30
a. Define PPC. What are its objectives?
b. Define the terms Routing, Loading and Scheduling?
c. What is Break Even Analysis? Write its assumptions
d. What is the role of operator within industry?
e. Write advantages and disadvantages of job production?
f. What are the different factors affecting Quality?
g. Write a note on Process sheet?
SECTION-C
Q3. Attempt any three questions. 3×10=30
i. What is dispatching? Write its functions and also discuss the different forms used during dispatching?
ii. What is ISO? What do you mean by ISO 9000? Write its characteristics and its aim?
iii. Differentiate b/w estimating and costing? Also define the different terms used in costing?
iv. Define production and productivity? What are the factors affecting productivity?
BIS stands for _____________
Process production is a ________ type of production.
Catalogue price = _______________
Rent of building, depreciation cost comes under __________ overhead.
 ______ is the process of predicting events, in advance.
Â
Depreciation
Quality circle
 Inspection
Follow up
Batch production
Production Planning and Costing 6th Sem dec 2016 Diploma Paper Click Here
PPC and its objectives.
Routing, Loading and Scheduling.
Break Even Analysis and its assumptions
Role of operator within industry.
Advantages and disadvantages of job production.
Different factors affecting Quality.
Short note on Process sheet.
Production Planning and Costing 6th Sem Dec 2016 Diploma Paper Click Here
Dispatching and its functionsÂ
Discuss the different forms used during dispatching.
ISO and ISO 9000.Write its characteristics and its aim.
Differentiate b/w estimating and costing.
Production and productivity
Factors affecting productivity.