QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

Download Previous Year Question paper of QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

                                      SECTION-A

Q1. Attempt any Three questions.                                                                    5×3=15

a. Find out the dry material required for 100sq m cemetery plaster 1:4 (1.25 cm thick)
b. What is valuation? Give the purpose of valuation?
c. Define tender and earnest money?
d. Differentiate between security deposit and retention money?
e. What is rough estimate?
f. Write note on sinking fund?
g. Discuss the following terms
i) Scrap value ii) Market value iii) Rental return method of valuation

                                       SECTION-B

Q2. Attempt any one question.                                                      1×10=10

i. Prepare a preliminary estimate of a posh building with the following data
Plinth area rateRs 2500/sq m
Architectural design and drawing 1.5% of building cost
Water supply and sanitary Installation 10% of the cost of building
Electricity Installation Including fans etc. 14% of the cost of building
Extra for other service 6% overall Contingency 5% overall Supervision charges 3% overall
ii. What are the specifications of earth work in excavation of foundation?
iii. What is contractor system? What are types of contractor system? Explain each one in detail?
iv. Work out the quantities of following items from the given diagram
a) Excavation of foundation b) Cement Concrete 1:6:18 in foundation
c) Masonry in foundation and plinth d) Masonry in superstructure

Dry material required for 100sq m cemetery plaster 1:4 (1.25 cm thick)

Valuation and purpose of valuation.

Tender and earnest money.

Differentiate between security deposit and retention money.

Rough estimate.

i) Scrap value

ii) Market value

iii) Rental return method of valuation

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper Click Here

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

Prepare a preliminary estimate of a posh building with the following data
Plinth area rateRs 2500/sq m
Architectural design and drawing 1.5% of building cost
Water supply and sanitary Installation 10% of the cost of building
Electricity Installation Including fans etc. 14% of the cost of building
Extra for other service 6% overall Contingency 5% overall Supervision charges 3% overall

Related Post

Specifications of earth work in excavation of foundation.

a) Excavation of foundation b) Cement Concrete 1:6:18 in foundation
c) Masonry in foundation and plinth d) Masonry in superstructure

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper Contact Us

Table of Contents

MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
ENGINEERING CLASSES
ER.JASWINDER KUMAR
er.jaswinder kumar
Senior Lecturer
admin: Hello Friends, I am Jaswinder Kumar Working as HOD (Senior Lecturer) at Polytechnic Engineering College. I Have Three Youtube Channel names as 1.JK Smart Classes 2.JK Smart Lecture 3.Engineering Classes for Helps the Class 12, Diploma, and B.tech Student To achieve the desired goal in an easy way.

This website uses cookies.

Read More