Quantity Surveying & Valuation 6th Sem/Civil/Dec 2016 Diploma Paper

Download Previous Year Diploma Paper of Quantity Surveying & Valuation 6th Sem/Civil/Dec 2016 Diploma Paper

Quantity Surveying & Valuation 6th Sem/Civil/Dec 2016 Diploma Question Paper

                                      SECTION-A

Q1) State the unit of measurement for following  10×1.5=15     

     1. Lime concrete
     2. Steel truss
     3. Door and windows
     4. Drain
     5. Welding
     6. D.P.C.
     7. Snowcem
     8. Skirting
     9. Brick work
    10. Expansion joints

    

                                      SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30   
    1. Find out the dry materials required for 10sqm cement plaster 1:4 (1.25 cm thick)?
   2. Describe in brief the various specifications of first class building?
   3. What do you mean by tools and plant? Give its comparison with stock?
   4. Define tender and earnest money?
   5. What is administrative approval? Why it is important while starting a project?
   6. Write a note on piece work agreement?
   7. What is valuation? Give the purpose of valuation

                                     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

    1. Workout the analyses of rate for cement concrete 1:2:4 in slab. Labour for 10cum cement concrete is 1mason @ 450 Rs/day, 15 mazdoor @ 300 Rs/day, 2 bhisti @ 200 Rs/day. (Assume any other required data)
   2. A short link road to be constructed entirely in cutting at a uniform rising gradient 1 in 30 the N.S.L. are given below

Rd

N.S Level

0

70.50

30

69.30

60

71.40

90

74.00

120

75.10

150

76.10

If the formation level at Rd 0 is 75 meters, estimate the quantity of cutting for a formation width of 10m. The side slope is 2:1 and there is no cross slope. Also find out the cost of cutting @450.00/cum.

    3. State the following terms
      (a) Sinking fund           (d) Gross income
      (b) Scrap value              (e) Year purchase
      (c) Capital cost

   4. Work out the quantities of the following items from the given drawing.
     (a) Excavation for foundation
     (b) Cement concrete 1:6:18 in foundation
      (c) Brick masonry in foundation and plinth

Quantity Surveying & Valuation 6th Sem/Civil/Dec 2016 Diploma Solved Question Paper

                                      SECTION-A

Q1) State the unit of measurement for following  10×1.5=15     

     1. Lime concrete
     2. Steel truss
     3. Door and windows
     4. Drain
     5. Welding
     6. D.P.C.
     7. Snowcem
     8. Skirting
     9. Brick work
    10. Expansion joints

    

Quantity Surveying & Valuation 6th Sem/Civil /dec 2016 Diploma Paper

MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ENGINEERING CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
er.jaswinder kumar
Senior Lecturer

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top