Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Paper

Download Previous Year Diploma Paper of Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Paper

Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Solved Question Paper

                                      SECTION-A

Q1. a) Fill in the Blanks.                                             15×1=15     

     i. Number of bricks required for 1 Cu.m brick masonry is ____________
    ii. Capitalized value = net annual rent × _________
   iii. On acceptance of the tender % of the tendered amount has to be paid as                      security money.
    iv. A reasonable profit usually % for contractor is included in the analysis of                  rates.
    v. Total Dry material required for 1 cu.m cement concrete is ______ cu.m.

b) State the unit of measurement for the following.

     vi. Earthwork
    vii. Flooring
    viii. Distempering
      ix. D.P.C
       x. Steel work
      xi. Brick Work
     xii. Electric Fitting
    xiii. Welding
     xiv. Skirting
      xv. R.C.C. slab roofing

                                      SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30   
   a. What is valuation? Give the purpose of valuation.
   b. What are the factors considered while preparing the analysis of rates?
   c. Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
   d. Find out the dry material required for 1 cu.m cement concrete 1:2:4.
   e. Define tender. Write the name of various tender documents.
   f. Define contractor. What are essential qualifications of a contractor?
   g. Write a short note on Scrap value and Earnest money.
   h. Write a short note on different Measurement Books.
   i. Write a short note on Depreciation and Muster Roll.

                                     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

    Q3. Prepare a preliminary estimate of a building having plinth area equal to                    2000 sq.m. Given that:-
      a. Plinth area rate – Rs. 2500/- per sq.
      b. Extra for Architectural work – 1½% of the building cost.
      c. Extra for Electrical Installation (10%), + Water supply and sanitary                               installations (6%) = 10+6=16% of the building cost.
      d. Extra for other services- 8% of the building cost.
      e. Contingencies and supervision charges 10%.
   Q4. Workout the analyses of rates per cu.m for Brick work 1:4 cement sand                    mortar in superstructure.Labour for 10cu.m brick work is 8 brick layers                    @ Rs. 350/- per day, 15 mazdor @ Rs. 200/- , 2 Bhisti @ Rs. 250/- per day.
         Rate of material:- cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks = Rs.           3.5 per brick.
    Q5. Define an estimate. Give its importance or objectives. Name the various                  types of estimate.
    Q6. What is contract? Explain the different type of contract.

     Q7. Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following dates:

Rd

N.S. level

Formation Level

0

205.00

210.00

30

205.60

 

60

206.00

 

90

206.80

 

    The formulation is in a downward gradient of 1 in 30. Formulation width is 10 meters and side slope 2:1(Horizontal: Vertical) Rate of earthwork is Rs. 400.00% cu.m

 

   Q8. Work out the quantity of following items from the given drawing:-

  1. Excavation for foundation

  2. Cement concrete 1:6:18 in foundation

  3. Mud Masonry in foundation and plinth

  4. Mud Masonry in super structure

    QSV MAY 2019 Diploma Paper 

Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Question Paper

                                      SECTION-A

Q1. a) Fill in the Blanks.                                             15×1=15     

     i. Number of bricks required for 1 Cu.m brick masonry is ____________
    ii. Capitalized value = net annual rent × _________
   iii. On acceptance of the tender % of the tendered amount has to be paid as                      security money.
    iv. A reasonable profit usually % for contractor is included in the analysis of                  rates.
    v. Total Dry material required for 1 cu.m cement concrete is ______ cu.m.

b) State the unit of measurement for the following.

     vi. Earthwork
    vii. Flooring
    viii. Distempering
      ix. D.P.C
       x. Steel work
      xi. Brick Work
     xii. Electric Fitting
    xiii. Welding
     xiv. Skirting
      xv. R.C.C. slab roofing

Valuation and purpose of valuation.

Factors considered while preparing the analysis of rates

Dry material for 1 cu.m brick masonry in cement sand mortar 1:5.

Find out the dry material required for 1 cu.m cement concrete 1:2:4.

Tender and name of various tender documents.

Contractor and essential qualifications of a contractor

Short note on Scrap value and Earnest money.

Short note on different Measurement Books.

Short note on Depreciation and Muster Roll.

Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Solved Paper Click Here

Quantity Surveying & Valuation 6th Sem/Civil /May 2019 Diploma Paper

MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ENGINEERING CLASSES
ER.JASWINDER KUMAR
JK SMART CLASSES
er.jaswinder kumar
Senior Lecturer

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top